Works in Khulna Hi-Tech Park

1. Construction of Internal Road and Land Development:
Progress: The works of land development is completed. Currently the Water Bound Macadam (WBM) of road is going on and the whole works will be completed by June/2018.

2. Installation of Street Light Line:
Progress: The installation of street light will be completed by June/2018.

3. Construction of Boundary Wall and Gate:
Progress: The construction is going on. Out of 164 pillars 152 is already made and within June/2018 it will be completed.

4. Construction of ICT Incubation & Training Center:
Progress: Construction of piling is going on. The whole works will be completed by March/2019.